A23 resurfacing works

National Highways are resurfacing the A23 between Bolney and Patchham.

Resurfacing works will be undertaken in two phases, overnight between the hours of 8pm to 6am Monday to Friday.

Phase one will be overnight closures to the southbound carriageway from Bolney to Muddleswood, phase two will be from Bolney to Patcham.

Phase one Bolney to Muddleswood southbound overnight closures:

  • Monday 2 February for five nights

Phase two Bolney to Patcham southbound overnight closures:

  • Monday 9 February for five nights
  • Monday 16 February for five nights
  • Monday 23 February for five nights

Diversions:

Traffic will be diverted via – A272, A24, A283 and A27

There will also be localised diversion routes in place for adjoining roads onto the A23 southbound carriageway.

Kind regards

South East Scheme Communications